Skip to content
This article is for educational purposes. We encourage you to verify with official sources.

Ever wondered how electricity from the power plant in Point Lisas reaches your phone charger in Chaguanas without frying it first? It's all thanks to substations — those unsung heroes of the grid that step down voltage, protect equipment, and keep the lights on across Trinité-et-Tobago. From the industrial zone in San Fernando to the tourist resorts of Tobago, every reliable electrical system depends on smart substation design. But here's the catch: CSEC and CAPE examiners don't just want you to memorize transformer ratios — they want you to APPLY that knowledge to real T&T scenarios. That's why we've cooked up 10 meaty exercises using local currency (TTD), real distances between our major towns, and problems you'd actually face working for T&TEC or an industrial client. Whether you're calculating short-circuit currents for a Tobago substation or designing lightning protection for a facility near Pitch Lake, these exercises will turn textbook theory into practical power engineering skills. Ready to power up? Let's go.

Transformer Rating Calculation for San Fernando Substation

facileapplication

The new 15 MVA substation in San Fernando steps down voltage from 66 kV to 11 kV. Calculate the current ratings on both the high-voltage and low-voltage sides of the main transformer.

Given data

STransformer rating15MVA
V_HVHigh voltage side66kV
V_LVLow voltage side11kV

Find

  • I_HV — High voltage side current (A)
  • I_LV — Low voltage side current (A)

Progressive hints

Hint 1

Start by writing the formula for three-phase power: S=3VI

Hint 2

Rearrange to solve for current: I=S/(3V)

Hint 3

Remember to convert MVA to VA before calculation

Full solution
  1. Given data — The transformer rating is 15 MVA stepping down from 66 kV to 11 kV.
  2. Formula for three-phase current — For a three-phase system, the power is given by S=3VLIL where VL is line-to-line voltage and IL is line current.
    S=3VLIL
  3. Convert MVA to VA — Convert the transformer rating from MVA to VA: 15 MVA = 15 000 000 VA.
    S=15 000 000 VA
  4. Calculate HV side current — On the high voltage side, VHV=66 kV=66 000 V. Using IHV=S/(3VHV):
    IHV=15 000 0003×66 000
  5. Calculate LV side current — On the low voltage side, VLV=11 kV=11 000 V. Using ILV=S/(3VLV):
    ILV=15 000 0003×11 000

IHV=131.2 A, ILV=787.3 A

→ High voltage side current: 131.2 A, Low voltage side current: 787.3 A

Power Loss in Transmission Line to Chaguanas

facileapplication

Electricity is transmitted from the power plant in Point Lisas to a substation in Chaguanas at 132 kV. Given a load of 50 MW at 0.9 power factor lagging, calculate the power loss in the 30 km transmission line with conductor resistance of 0.1 Ω/km.

Given data

PLoad power50MW
VTransmission voltage132kV
dLine length30km
rConductor resistance per km0.1\Omega/km
pfPower factor0.9

Find

  • P_loss — Power loss (kW)

Progressive hints

Hint 1

First calculate the line current using P=3VIcosϕ

Hint 2

Then calculate total line resistance: Rtotal=r×d

Hint 3

Power loss is Ploss=3I2Rline for a three-phase system

Full solution
  1. Given data — Power transmitted is 50 MW at 132 kV over 30 km with conductor resistance 0.1 Ω/km and power factor 0.9.
  2. Calculate line current — Using P=3VIcosϕ, solve for current I where P=50 MW=50 000 000 W and V=132 000 V:
    I=P3Vcosϕ=50 000 0003×132 000×0.9
  3. Calculate total line resistance — Total resistance for the 30 km line: Rtotal=0.1 Ω/km×30 km=3 Ω.
    Rtotal=3 Ω
  4. Calculate power loss — For a three-phase system, power loss is Ploss=3I2Rline:
    Ploss=3I2Rtotal

Ploss=1 296 kW

→ Power loss: 1.3 MW (1 296 kW)

Substation Layout for Arima Housing Development

moyenmodeling

A new housing development in Arima requires a 10 MVA substation to step down from 33 kV to 11 kV. Determine the main transformer rating, select appropriate circuit breaker ratings for both sides, and specify the number of outgoing 11 kV feeders needed, considering 20% future load growth.

Given data

S_loadCurrent load10MVA
V_inIncoming voltage33kV
V_outOutgoing voltage11kV
growthFuture load growth20%

Find

  • S_transformer — Transformer rating (MVA)
  • I_breaker_HV — HV breaker rating (kA)
  • I_breaker_LV — LV breaker rating (kA)
  • n_feeders — Number of outgoing feeders

Progressive hints

Hint 1

Start by calculating the future load including 20% growth

Hint 2

Transformer rating should be at least 20% higher than current load for future expansion

Hint 3

Circuit breaker ratings should be based on maximum fault current, typically 2-3 times normal current for safety margin

Hint 4

Each outgoing feeder typically carries 2-4 MVA in residential areas

Full solution
  1. Calculate future load — With 20% growth, future load = 10 MVA × 1.20 = 12 MVA.
    Sfuture=10 MVA×1.20=12 MVA
  2. Select transformer rating — Choose a standard transformer rating slightly above future load. Common ratings are 12.5 MVA or 15 MVA. We'll select 15 MVA for this design.
    Stransformer=15 MVA
  3. Calculate HV side current — High voltage side current for 15 MVA at 33 kV: IHV=S/(3VHV)
    IHV=15 000 0003×33 000
  4. Calculate LV side current — Low voltage side current for 15 MVA at 11 kV: ILV=S/(3VLV)
    ILV=15 000 0003×11 000
  5. Select circuit breaker ratings — Circuit breakers should have continuous rating above normal current and interrupting rating above maximum fault current. Typical practice is to select breakers with ratings 2-3 times the normal current for safety.
    Ibreaker_HV=2.5×IHV=2.5×262.4 A=656 A
  6. Determine number of feeders — Each outgoing feeder typically carries 2-4 MVA. For 12 MVA future load, we need at least 3 feeders (12 MVA / 4 MVA per feeder = 3 feeders).
    nfeeders=12 MVA4 MVA/feeder=3

Stransformer=15 MVA, Ibreaker_HV=656 A, Ibreaker_LV=1 968 A, nfeeders=3

→ Transformer rating: 15 MVA, HV breaker rating: 656 A, LV breaker rating: 1 968 A, Number of outgoing feeders: 3

Short-Circuit Current Calculation for Tobago Substation

moyenanalysis

A three-phase fault occurs on the 11 kV busbar of the Tobago substation. Calculate the prospective short-circuit current and determine the required circuit breaker interrupting rating. The system has a 15 MVA, 33/11 kV transformer with 10% impedance, and the short-circuit level at the 33 kV bus is 500 MVA.

Given data

S_transformerTransformer rating15MVA
V_HVHigh voltage side33kV
V_LVLow voltage side11kV
Z_transformerTransformer impedance10%
SC_level_HVShort-circuit level at 33 kV bus500MVA

Find

  • I_sc_LV — Short-circuit current at LV bus (kA)
  • I_breaker_rating — Required breaker interrupting rating (kA)

Progressive hints

Hint 1

Calculate the equivalent system impedance at the 33 kV bus using the given short-circuit level

Hint 2

Combine transformer impedance with system impedance using the formula for parallel impedances

Hint 3

Short-circuit current is Isc=Vphase/Ztotal where Ztotal is the total impedance to the fault point

Hint 4

Breaker rating should be at least equal to the calculated short-circuit current

Full solution
  1. Calculate system impedance at 33 kV — System impedance at 33 kV bus: Zsys=V2/Ssc where V=33 kV and Ssc=500 MVA:
    Zsys=V2Ssc=(33 000)2500 000 000=2.178 Ω
  2. Calculate transformer impedance — Transformer impedance on its own base: Ztransformer=Zpu×(VLV2/Stransformer) where Zpu=10%=0.10 and Stransformer=15 MVA:
    Ztransformer=0.10×(11 000)215 000 000=0.807 Ω
  3. Convert transformer impedance to 33 kV base — To combine impedances, convert transformer impedance to the 33 kV base: Ztransformer_33kV=Ztransformer×(VHV2/VLV2):
    Ztransformer_33kV=0.807×332112=7.263 Ω
  4. Combine impedances — Total impedance to fault at 11 kV bus: Ztotal=Zsys+Ztransformer_33kV=2.178+7.263=9.441 Ω
    Ztotal=9.441 Ω
  5. Calculate short-circuit current — Short-circuit current at 11 kV bus: Isc=Vphase/Ztotal where Vphase=11 000/3:
    Isc=11 000/39.441=672.3 A
  6. Determine breaker rating — The circuit breaker should have an interrupting rating at least equal to the calculated short-circuit current. Standard ratings are 8 kA, 12.5 kA, 16 kA, 25 kA, etc. We select the next standard rating above 0.672 kA, which is 8 kA.
    Ibreaker_rating=8 kA

Isc_LV=0.672 kA, Ibreaker_rating=8 kA

→ Prospective short-circuit current: 0.672 kA, Required breaker interrupting rating: 8 kA

Economic Analysis for San Fernando Substation Upgrade

moyenoptimization

The San Fernando substation needs an upgrade costing 2 500 000 TTD to improve efficiency and reliability. Calculate the simple payback period in years given annual energy savings of 12 GWh and an electricity tariff of 0.45 TTD/kWh. Assume no salvage value and ignore discounting for this calculation.

Given data

C_upgradeUpgrade cost2\ 500\ 000TTD
E_savedAnnual energy savings12GWh
tariffElectricity tariff0.45TTD/kWh
discount_rateDiscount rate0%

Find

  • T_payback — Simple payback period (years)

Progressive hints

Hint 1

First calculate annual monetary savings by multiplying energy saved by tariff

Hint 2

Payback period is upgrade cost divided by annual savings

Hint 3

Convert GWh to kWh for consistent units

Full solution
  1. Convert energy savings to kWh — 12 GWh = 12 000 000 kWh.
    Esaved=12 000 000 kWh
  2. Calculate annual monetary savings — Annual savings = Energy saved × Tariff = 12 000 000 kWh × 0.45 TTD/kWh:
    Savingsannual=12 000 000×0.45=5 400 000 TTD
  3. Calculate payback period — Simple payback period = Upgrade cost / Annual savings = 2 500 000 TTD / 5 400 000 TTD/year:
    Tpayback=2 500 0005 400 000

Tpayback=0.46 years

→ Simple payback period: 0.46 years (approximately 5.5 months)

Lightning Protection for Substation near Pitch Lake

difficilemodeling

Design a lightning protection system for a substation located 5 km from Pitch Lake. Determine the number of lightning arresters required and specify the grounding grid design parameters including conductor length, mesh size, and expected ground resistance. Given soil resistivity is 100 Ω·m, lightning strike current is 30 kA, equipment basic insulation level (BIL) is 95 kV, and substation dimensions are 50 m × 40 m.

Given data

rhoSoil resistivity100\Omega\cdot m
I_lightningLightning strike current30kA
BILEquipment BIL95kV
LSubstation length50m
WSubstation width40m
dDistance from Pitch Lake5km

Find

  • n_arresters — Number of lightning arresters
  • L_grounding — Grounding conductor length (m)
  • mesh_size — Grounding grid mesh size (m)
  • R_ground — Expected ground resistance (\Omega)

Progressive hints

Hint 1

Start by calculating the required protective level of arresters based on equipment BIL

Hint 2

Use the rolling sphere method to determine arrester placement and number

Hint 3

For grounding grid design, use the simplified formula for ground resistance of a rectangular grid

Hint 4

Typical mesh size is 5-10 m for substations

Full solution
  1. Calculate protective level requirement — The protective level of arresters should be less than 80% of BIL for adequate protection: Vprotective<0.8×BIL=0.8×95 kV=76 kV.
    Vprotective<76 kV
  2. Select arrester rating — Choose standard arrester rating below 76 kV. Common ratings are 72 kV or 69 kV. We'll select 72 kV arresters.
    Varrester=72 kV
  3. Determine number of arresters using rolling sphere method — Using the rolling sphere method with sphere radius based on strike current (30 kA corresponds to ~20 m radius), place arresters at corners and along perimeter. For a 50 m × 40 m substation, 8 arresters (one at each corner and one mid-side on each long side) provide adequate coverage.
    narresters=8
  4. Design grounding grid — For a rectangular grid, ground resistance can be approximated by R=ρ/(4r) for a circular grid of equivalent area, where r=A/π and A=L×W. For a rectangular grid, a more accurate formula is R=ρ[ln(2L/W)+1]/(2πL) for L >> W.
    R=ρ2πL[ln(2LW)+1]
  5. Calculate ground resistance — Substituting values: L=50 m,W=40 m,ρ=100 Ωm:
    R=1002π×50[ln(2×5040)+1]=0.318×[ln(2.5)+1]=0.318×1.916=0.61 Ω
  6. Specify grid parameters — Typical mesh size is 5-10 m. For this substation, use 6 m mesh size. Total conductor length for a 50 m × 40 m grid with 6 m spacing: approximately 2 × (50/6 + 40/6) × 6 m ≈ 180 m of conductor.
    Lgrounding=180 m, meshsize=6 m

narresters=8, Lgrounding=180 m, meshsize=6 m, Rground=0.61 Ω

→ Number of lightning arresters: 8, Grounding conductor length: 180 m, Mesh size: 6 m, Expected ground resistance: 0.61 Ω

Harmonic Filter Design for Point Lisas Industrial Zone

difficileanalysis

The new aluminum smelter in Point Lisas is injecting significant 5th harmonic current into the 11 kV system. Design a passive single-tuned filter to reduce total harmonic distortion (THD) to below 5%. Given the load is 20 MVA at 11 kV, the 5th harmonic current is 15% of the fundamental current, and the system short-circuit level at 11 kV is 250 MVA with 5% impedance.

Given data

S_loadLoad power20MVA
VSystem voltage11kV
hHarmonic order5
I_h_percHarmonic current percentage15%
SC_levelShort-circuit level250MVA
Z_sysSystem impedance percentage5%

Find

  • Q_filter — Filter reactive power rating (MVAr)
  • f_tune — Filter tuning frequency (Hz)
  • THD_after — THD after filter installation (%)

Progressive hints

Hint 1

First calculate the fundamental and harmonic currents

Hint 2

Determine the required filter reactive power rating to achieve target THD

Hint 3

A single-tuned filter is tuned to the harmonic frequency: ftune=h×ffundamental

Hint 4

Filter impedance at fundamental frequency provides reactive power support

Full solution
  1. Calculate fundamental current — Fundamental current: Ifund=S/(3V)=20 000 000/(3×11 000)=1 049.7 A.
    Ifund=20 000 0003×11 000=1 049.7 A
  2. Calculate 5th harmonic current — 5th harmonic current: I5=0.15×Ifund=0.15×1 049.7=157.5 A.
    I5=0.15×1 049.7=157.5 A
  3. Determine system impedance at 11 kV — System impedance: Zsys=V2/Ssc=(11 000)2/250 000 000=0.484 Ω. In per unit on 20 MVA base: Zsys_pu=0.05 pu (given).
    Zsys=0.484 Ω
  4. Calculate required filter rating — To achieve THD < 5%, the filter should provide reactive power to reduce harmonic voltage distortion. A typical design targets harmonic current reduction by 70-80%. We'll design for 75% reduction.
    I5_after=0.25×I5=0.25×157.5=39.4 A
  5. Filter reactive power rating — Filter reactive power rating should match the fundamental current component: Qfilter=3VIfund=1.732×11 000×1 049.7=20 MVAr (approximately equal to load MVA rating for unity power factor correction).
    Qfilter=20 MVAr
  6. Filter tuning frequency — For 5th harmonic filter: ftune=h×ffundamental=5×50 Hz=250 Hz.
    ftune=250 Hz
  7. Calculate expected THD — With 75% harmonic current reduction, the harmonic voltage distortion is approximately Vh=I5_after×Zsys=39.4×0.484=19.1 V. Fundamental voltage is Vfund=11 000/3=6 351 V. THD = (Vh/Vfund)×100%=(19.1/6 351)×100%=0.30%.
    THD=19.16 351×100%=0.30%

Qfilter=20 MVAr, ftune=250 Hz, THDafter=0.30%

→ Filter reactive power rating: 20 MVAr, Tuning frequency: 250 Hz, Expected THD after filter: 0.30%

Reliability Analysis for Chaguanas Substation

difficileoptimization

Analyze the current reliability of the Chaguanas substation with 2 transformers and 8 circuit breakers. Calculate SAIFI and SAIDI, then propose upgrades to achieve SAIFI < 1.5 interruptions/year and SAIDI < 2 hours/year. Given failure rates: transformer 0.02 failures/year, breaker 0.01 failures/year; repair times: transformer 168 hours, breaker 24 hours.

Given data

n_transformerNumber of transformers2
n_breakerNumber of circuit breakers8
lambda_TTransformer failure rate0.02failures/year
lambda_BBreaker failure rate0.01failures/year
r_TTransformer repair time168hours
r_BBreaker repair time24hours

Find

  • SAIFI_current — Current SAIFI (interruptions/customer/year)
  • SAIDI_current — Current SAIDI (hours/customer/year)
  • upgrades — Proposed upgrades

Progressive hints

Hint 1

SAIFI = (sum of failure rates × number of components) / total customers

Hint 2

SAIDI = (sum of failure rates × repair time × number of components) / total customers

Hint 3

Assume 10 000 customers for this substation

Hint 4

For SAIFI < 1.5, total failure rate must be less than 1.5 × 10 000 = 15 000 failures/year

Hint 5

Upgrades could include adding redundant transformers or improving maintenance

Full solution
  1. Calculate total failure rates — Total failure rate = (ntransformer × lambdaT) + (nbreaker × lambdaB) = (2 × 0.02) + (8 × 0.01) = 0.04 + 0.08 = 0.12 failures/year.
    λtotal=0.12 failures/year
  2. Calculate SAIFI — SAIFI = lambdatotal = 0.12 interruptions/customer/year (assuming each failure affects all customers equally).
    SAIFI=0.12 interruptions/customer/year
  3. Calculate total repair time contribution — Total repair time contribution = (ntransformer × lambdaT × rT) + (nbreaker × lambdaB × rB) = (2 × 0.02 × 168) + (8 × 0.01 × 24) = 6.72 + 1.92 = 8.64 hours/year.
    SAIDIcontribution=8.64 hours/year
  4. Calculate SAIDI — SAIDI = 8.64 hours/customer/year.
    SAIDI=8.64 hours/customer/year
  5. Compare with targets — Current SAIFI (0.12) is below target (1.5), but current SAIDI (8.64 hours) exceeds target (2 hours). The main contributor is transformer repair time.
  6. Propose upgrades — To reduce SAIDI, add a third transformer as backup (reducing transformer failure rate impact) and improve maintenance procedures to reduce repair time. Adding a third transformer reduces effective failure rate contribution from transformers by a factor of 3.
    Proposed: Add 1 transformer, reduce repair time to 72 hours
  7. Calculate upgraded reliability — With 3 transformers and reduced repair time: New lambdaT_contribution = (3 × 0.02 × 72) / 10 000 = 0.0432 hours/customer/year. Total SAIDI contribution = 0.0432 + 1.92 = 1.96 hours/year, which meets the target.
    SAIDIupgraded=1.96 hours/year

SAIFIcurrent=0.12, SAIDIcurrent=8.64 hours, SAIDIupgraded=1.96 hours

→ Current SAIFI: 0.12 interruptions/year, Current SAIDI: 8.64 hours/year, Proposed upgrades: Add one transformer, reduce repair time to 72 hours, Resulting SAIDI: 1.96 hours/year

Solar Farm Connection to Grid via La Brea Substation

difficilemodeling

Design the interface between a 10 MW solar farm in La Brea and the existing 33 kV grid at La Brea substation. Specify the transformer rating, protection coordination requirements, and reactive power control strategy for bidirectional power flow.

Given data

P_solarSolar farm capacity10MW
V_gridGrid voltage33kV
eta_inverterInverter efficiency97%
SC_levelGrid short-circuit level250MVA
V_inverterInverter output voltage400V

Find

  • S_transformer — Interface transformer rating (MVA)
  • V_primary — Transformer primary voltage (kV)
  • V_secondary — Transformer secondary voltage (kV)
  • Q_required — Required reactive power capability (MVAr)
  • Protection_requirements — Protection scheme

Progressive hints

Hint 1

Solar farms typically use inverters that output at 400 V, so a step-up transformer is needed

Hint 2

Transformer rating should account for inverter efficiency and potential overloading

Hint 3

Protection must handle both import and export of power (bidirectional)

Hint 4

Grid codes typically require solar farms to provide reactive power support (e.g., power factor 0.95 lagging to 0.95 leading)

Hint 5

Consider using a 12 MVA transformer for 10 MW solar farm to allow for future expansion

Full solution
  1. Calculate inverter output power — Inverter output power = Solar capacity × efficiency = 10 MW × 0.97 = 9.7 MW.
    Pinverter=10 MW×0.97=9.7 MW
  2. Select transformer rating — Choose a standard transformer rating slightly above inverter output. A 12 MVA transformer provides adequate capacity and future expansion margin.
    Stransformer=12 MVA
  3. Determine transformer voltages — Standard configuration: Primary 33 kV (grid connection), secondary 400 V (inverter connection).
    Vprimary=33 kV, Vsecondary=400 V
  4. Calculate required reactive power capability — Grid codes typically require solar farms to operate at power factor between 0.95 lagging and 0.95 leading. For 9.7 MW output, reactive power capability: Q=P×tan(cos1(0.95))=9.7×0.329=3.2 MVAr.
    Qrequired=9.7×tan(cos1(0.95))=3.2 MVAr
  5. Protection coordination — Protection scheme must include: directional overcurrent relays (for bidirectional power flow), under/over voltage protection, frequency protection, anti-islanding protection, and reactive power control. Use numerical relays with communication to substation SCADA system.
  6. Reactive power control strategy — Implement Volt/VAR control strategy: Inverter should absorb reactive power when voltage is high and supply reactive power when voltage is low, within the ±3.2 MVAr capability. Use droop control with 1% droop characteristic.
    Droop=1% (Vref=33 kV, Qmax=±3.2 MVAr)

Stransformer=12 MVA, Vprimary=33 kV, Vsecondary=400 V, Qrange=±3.2 MVAr

→ Transformer rating: 12 MVA, Primary voltage: 33 kV, Secondary voltage: 400 V, Reactive power capability: ±3.2 MVAr, Protection: Directional overcurrent, Volt/VAR control with 1% droop

SCADA System Design for Tobago Substation

difficileconstruction

Design a SCADA system for remote monitoring and control of the Tobago substation. Specify the communication architecture, protocols, and provide a cost estimate. The substation has 120 analog inputs, 250 digital inputs, and is located on a remote island with existing microwave link to Trinidad.

Given data

n_analogNumber of analog inputs120
n_digitalNumber of digital inputs250
locationSubstation locationTobago
comm_existingExisting communicationMicrowave link to Trinidad

Find

  • SCADA_architecture — SCADA architecture type
  • communication_protocols — Communication protocols
  • cost_estimate — Estimated total cost (TTD)

Progressive hints

Hint 1

For a remote island substation, consider a hierarchical SCADA architecture with local RTU and remote HMI

Hint 2

Use IEC 61850 protocol for substation automation and communication

Hint 3

Include cost for RTU, communication equipment, HMI software, engineering, and installation

Hint 4

Typical cost ranges: RTU 50 000-150 000 TTD, Communication equipment 30 000-80 000 TTD, HMI software 100 000-200 000 TTD, Engineering 150 000-300 000 TTD

Full solution
  1. Select SCADA architecture — For a remote substation, use a hierarchical architecture: Local RTU at Tobago substation, Remote HMI in Trinidad control center, connected via microwave link. This provides local control capability and remote monitoring.
    Architecture: Hierarchical SCADA with local RTU and remote HMI
  2. Specify communication protocols — Use IEC 61850 for substation automation (GOOSE messaging for fast protection signals, MMS for monitoring). Use IEC 60870-5-104 for remote telemetry over the microwave link. Use DNP3 for integration with existing systems if needed.
    Protocols:IEC61850(substation),IEC608705104(remote),DNP3(legacyintegration)
  3. RTU selection and configuration — Select an RTU with capacity for 120 analog and 250 digital inputs. Typical RTU can handle 256 digital and 128 analog points. Configure the RTU for local control and monitoring.
    RTU capacity: 256 digital, 128 analog points
  4. Communication infrastructure — Use existing microwave link for data transmission. Add VPN encryption for security. Bandwidth requirement: approximately 2-5 Mbps for this I/O count.
    Bandwidth:25Mbps,Security:VPNencryption
  5. HMI software and integration — Select SCADA software with IEC 61850 support and remote access capability. Configure HMI screens for substation one-line diagram, alarm management, trending, and reporting.
    HMI: IEC 61850 compatible, remote access enabled
  6. Cost breakdown — Estimated costs: RTU (120 000 TTD), Communication equipment (50 000 TTD), HMI software license (150 000 TTD), Engineering and configuration (200 000 TTD), Installation and commissioning (100 000 TTD), Contingency (30 000 TTD). Total: 650 000 TTD.
    Totalcost=120 000+50 000+150 000+200 000+100 000+30 000=650 000 TTD

SCADAarch=Hierarchical RTU+HMI, Protocols=IEC 61850/104/DNP3, Cost=650 000 TTD

→ SCADA architecture: Hierarchical with local RTU and remote HMI, Communication protocols: IEC 61850/IEC 60870-5-104/DNP3, Estimated cost: 650 000 TTD

Sources

  1. en.wikipedia.org
  2. www.jstor.org
  3. www.google.com
  4. scholar.google.com
  5. jemena.com.au
  6. www.theguardian.com
  7. www.messynessychic.com
  8. www.metacafe.com
  9. id.ndl.go.jp
  10. aleph.nkp.cz